10/16/2007 Our new addition arrives and with the help of our friends at J&B Mechanical, all is offloaded 2 hours later.

                                 

The picture on the left shows work progressing on the foundation. The picture on the right shows our existing hangar, the addition will be to the right side of this view.

A new corporate hangar across the ramp from us.

No work today. Several tornados strike the surrounding area from a series of storms through out the evening of Oct. 18th, 2007. No damage at the airport.

Footers and Piers completed 10/27/2007

Plumbing in and awaiting inspection 10-29-2007. The plumbing passed the following day. Thanks to Scott Shelton and his crew from Shelton's Plumbing.

           

          

11-01-2007 Work began before sunup getting ready for the concrete. We told the fellow on the troweling machine, with the proper mods to the engine, and airfoils in place of the troweling blades, we may get that thing to fly. Thanks to Ricky Sloan and all the guys on the concrete crew.

       

       

11-03-2007 The steel begins to go up. J&B Mechanical brought out the boom truck to help again.

        

     

11/19/2007 We are under roof! Work continued today installing insulation and liner panel for the roof and added area outside the building.

      

        

       

11/27/2007 The liner panel for the ceiling is complete and looks great. Framing for the interior walls begins.

03/25/2008 It's been a while since our last update. The walls, electrical, and HVAC are all in place. A big thanks to McConnell Electric, Woodard Cooling and Heating and our own in house painting crew. Today, the crew from Industrial Floors and Coatings got started applying the finish to the floor.

  

  

 